Commissioning - Ziton ZP2-AF2-P Installation Manual

Hide thumbs Also See for ZP2-AF2-P:
Table of Contents

Advertisement

Commissioning

After the control panel and corresponding devices are installed and configured,
the system must be commissioned.
Check the following:
That the fire system is designed, installed, and configured in accordance with
all required regulations and standards
That the maximum alarm current in your installation does not exceed the
maximum current specifications of the power supply
That all equipment is correctly installed and tested and that all cabling
complies with the recommendations outlined in "Recommended cables" on
page 31
That all software functions are correctly programmed
That all installed detectors are appropriate for installation environment and
operate correctly
That all inputs and outputs operate correctly
That any input/output logic (rules and actions) configuration is correct
That the fire system is functioning correctly in standby and is not reporting
any alarms or faults
That under the alarm conditions (with all applicable devices activated), the
current consumption does not exceed the power supply specifications (if the
batteries are not activated the current consumption is within the
specifications)
ZP2-A Series Installation Manual
Chapter 3: Configuration and commissioning
133