Installing The Server On The Ball Bearing Rail Kit - Huawei FusionServer Pro 2288X V5 User Manual

Hide thumbs Also See for FusionServer Pro 2288X V5:
Table of Contents

Advertisement

FusionServer Pro 2288X V5 Server
User Guide

7.2.5.2 Installing the Server on the Ball Bearing Rail Kit

Before installing the server, ensure that the ball bearing rail kit is properly
installed. For details, see
Procedure
Step 1 Install the server.
At least two people are required to move the device. Otherwise, personal injury or
device damage may occur.
1.
2.
Issue 04 (2020-06-05)
NO TICE
Pull out the inner rails as far as they will go.
Figure 7-9 Pulling out an inner rail
Lift the server (at least two people are required), align the two mounting
screws on the rear part of the server with the holes on the inner rails, and
push the server horizontally until the server cannot move. See
Copyright © Huawei Technologies Co., Ltd.
7.2.4.3 Installing the Ball Bearing Rail
7 Installation and Configuration
Kit.
Figure
7-10.
79

Advertisement

Table of Contents
loading

This manual is also suitable for:

V100r005

Table of Contents