Figure 4-59 Connecting power cables (NetCol5000-C030/C032)
1.
2.
3.
4.
Step 4 Use a multimeter to check for a short circuit between L and N of AC1 and AC2.
Use a multimeter to check for a short circuit between L, N, and PE.
Step 5 Check that the cable connections are secure.
Step 6 Reinstall the cover of the electric control box.
----End

4.14.4 Teamwork Networking and Monitoring

Issue 06 (2022-12-15)
Remove screws from both ends of the clip to remove it.
Connect the cables with crimped terminals to the L, N, and PE.
NO TE
NetCol5000-C065 uses a common screwdriver to secure the cables, NetCol5000-C030/
C032 uses a 100-120 mm screwdriver to secure the cables.
Place the connected power cables vertically, use the clip to secure them in a
proper position, and use screws to secure the clip.
Fasten the power cable to the vertical pillar by cable ties every 150 mm to
200 mm.
If there is a short circuit, remove the cable and reconnect it using the method
described in
Step
3.2. After verifying the connection, perform
If there is no short circuit, perform
If the cable connections are loose, fasten the connections.
If the cable connections are secure, the connection is complete.
Copyright © Huawei Digital Power Technologies Co., Ltd.
Step
5.
4 Installation
Step
5.
81

Advertisement

Table of Contents
loading

This manual is also suitable for:

Netcol5000-c032Netcol5000-c065

Table of Contents