Step 1 Commission the UPS by referring to the related UPS user manual.
Step 2 Ensure that only the POWER indicator on the optional BSC card is on.
Step 3 On the UPS monitoring screen where the optional BSC card is installed, set BSC
mode to Opt. BSC card mode.
Step 4 Check that the valid phase voltage difference between UPS systems is less than 5
V.
----End
Issue 03 (2022-09-16)
4
LCD path: System Info. > Settings > System Settings
WebUI path: Monitoring > UPS System > Running Parameter > System
Settings