Erecting the Pole
1. Check whether the pole needs to be repainted. Repaint the damaged area
of the pole, and then use the crane to hoist the pole to the foundation.
11

Verifying the Installation

1. Check that the mounting kits are securely installed and all screws are tightened.
2. Check that all cables are reliably connected with correct polarity and there is no short circuit.
3. Check whether any screw holes are not installed with screws. If so, install screws at the holes.
4. Check that all idle cable holes in modules are protected with waterproof caps.
12

Power-On Commissioning

Powering On Modules
12.1
1. Check the indicators on the function module and lithium batteries. Ensure that the green indicators are blinking slowly and that the
yellow and red indicators are off.
2. If a problem is found, refer to the alarm definitions in the user manual for troubleshooting.
3. Observe the board indicators in the maintenance compartment.
2. Secure the pole to the foundation.
9
NOTE
Normally, The STAT, PWR,
and WIFI indicators on the
EG8P panel are: green.