2.5 INSERTION INTO THE PIT

Before inserting the bollard into the pit, complete the electrical
connections as shown in §2.4 and §3.1, check that these function
correctly, and also check the function of the safety devices (see "JE275
ELECTRONIC EQUIPMENT" 13).
In order to position the bollard in the pit (wait for at least 7 days for
the concrete to cure), remove the safety bar, pulling the cotter pin
out first 9-1 then the bar 9-2.
2
Screw the two male M20 eye bolts onto the upper part, as shown
in10, using them as hooking points for lifting with belts or chains.
Raise the bollard and place fully into the pit.
During this phase, take care to position the corrugated conduits
correctly so that they are not pinched between the pit and the bol-
lard frame
www.FastGateOpeners.com | (800) 878-7829 | Sales@FastGateOpeners.com
After you have fully inserted the bollard, resting it against the coun-
terframe, remove the two eye bolts 11-1 and fix the bollard in place
using the 24 TCEI M24x50 screws supplied with the pit.
!
IMPORTANT: Tighten the screws to a torque of 50Nm
1
1
9

2.6 FIXING THE TOP COVER

After fixing the bollard in place, complete the installation by position-
ing and fixing the top cover with the six M8x40 steel screws provided.