Operation
5.1.2

Complete commissioning

BA-Classic FL_en-US, 03.05.2018
— all errors have been rectified and
— the functional checks without medium have shown the required
smooth running and the desired direction of rotation, see
Ä Chapter 4.5 "Checks before commissioning" on page 79.
1.
Adhere to the manufacturers' operating manuals for all
attached control components.
2.
First, switch on all additional devices, especially those with
measurement and control functions relevant to safety.
3.
Open the pipe shut-off devices on the inlet and the outlet
side.
4.
Switch on the drive of the Börger machine.
5.
Check all pipe connectors, the quick-release cover, etc., for
leaks.
6.
Check that the function/display of all additional devices is
working properly.
7.
Check that the Börger machine runs quietly and vibration-
free. If the Börger machine or drive emits uneven, rattling
sounds, then the cause must be determined.
8.
Check the power consumption of the drive. Compare the
values with those in the drive operating manual.
9.
Check the development of noises and temperature on the
drive.
The Börger machine can be operated properly when all functions
run correctly and no leaks are detected.
NOTE!
Checklist for commissioning
A checklist for commissioning the Börger machine can be found
Ä Chapter 9.6 "Checklist for commissioning" on page 183.