www.ti.com
1
EVM Overview
1.1
Features
MSOP-8EVM Features:
•
Full-featured evaluation board for a variety of single-channel, 8-pin, micro-SOP, 14- to 16-bit, serial
output, ADCs
•
Onboard reference and buffer circuits
•
High-speed serial interface
•
Modular design for use with a variety of DSP and microcontroller interface boards
For use with a computer, the MSOP-8EVM-PDK is available. This kit combines the MSOP-8EVM board
with the DSP-based MMB0 motherboard, and includes
The MMB0 motherboard allows the MSOP-8EVM to be connected to the computer via an available USB
port. This manual shows how to use the MMB0 as part of the MSOP-8EVM-PDK, but does not provide
technical details on the MMB0 itself.
ADCPro is a program for collecting, recording, and analyzing data from ADC evaluation boards. It is based
on a number of plug-in programs, so it can be expanded easily with new test and data collection plug-ins.
The MSOP-8EVM-PDK is controlled by a plug-in that is executed in ADCPro.
This manual covers the operation of both the MSOP-8EVM and the MSOP-8EVM-PDK. It does not
describe the MMB0 motherboard in detail. Throughout this document, the abbreviation EVM and the term
evaluation module are synonymous with the MSOP-8EVM.
1.2
Introduction
The modular MSOP-8 evaluation module is an updated version of the popular Burr-Brown DEM-MSOP-8
evaluation board. The EVM is designed so that a single printed wiring board (PWB) supports a variety of
test configurations for high-speed 14- and 16-bit serial ADCs.
The modular EVM form factor allows for direct evaluation of the ADC performance and operating
characteristics. This EVM is compatible with the 5-6K Interface Board (SLAU104), also available from
Texas Instruments.
1.3
Related Documentation
Table 1
lists documents related to the MSOP-8EVM. To obtain a copy of any of these TI documents, call
the Texas Instruments Literature Response Center at (800) 477-8924 or the Product Information Center
(PIC) at (972) 644-5580. When ordering, identify this booklet by its title and literature number. Updated
documents can also be obtained through our website at www.ti.com.
EVM-Compatible Device Data Sheets
Application Notes/Additional Literature from TI
Op Amps for Everyone
Single and Bipolar Signal Conditioning Boards
SBAU140A – December 2008 – Revised February 2016
Submit Documentation Feedback
Table 1. Related Documentation
ADS8320
ADS8321
ADS8324
ADS8325
ADS8326
5-6K Interface Board
Copyright © 2008–2016, Texas Instruments Incorporated
ADCPro™ software
for evaluation.
Literature Number
SBAS108
SBAS123
SBAS172
SBAS226
SBAS343
Literature Number
SLOD006
SLAU104
SLAU105
MSOP-8EVM and MSOP-8EVM-PDK
EVM Overview
3
Need help?
Do you have a question about the MSOP-8EVM-PDK and is the answer not in the manual?
Questions and answers