Lutron Electronics DMW-LZC1 Installation And Maintenance Manual page 16

Lighting zone controller and lighting zone controller panels

Advertisement

Activating Loads in Bypass
A. Complete load and feed wiring.
See previous sections.
B. Check that the bypass jumpers are in place.
These jumpers protect from load faults and must
be used to check load wiring when it is installed
or modified.
Caution! Verify that the panel is fed from the
correct voltage. A feed miswire or loss of a
feed neutral can cause damage to the
equipment.
C. Turn circuit breaker 1 ON.
Large panels with main lugs have circuit
breakers integral to the panel; circuit breakers
for other panels are in distribution panels.
When power is turned on, the load(s) should
energize, the breaker should not trip, and total
load current must be within the circuit breaker's
limit and less than or equal to 16 A.
In a main lug panel, circuit breaker 1 powers
Circuit 1's LZC and load(s). Check that the
Power LED on the LZC is ON. If the Power LED
is OFF, turn OFF the control circuit breaker
(breaker 1) and check for loose wires or
miswires in the panel.
D. Turn next circuit breaker ON.
The corresponding load should energize, the
breaker should not trip, and total load current
must be within the circuit breaker's limit and less
than or equal to 16 A. The power LED on the
corresponding LZC should be on.
E. Repeat step 'D' for each circuit with
completed load wiring.
16
Installation Guide for Lighting Zone Controllers
AC RMS current
Bypass
jumper
This page applies to:
Small
Std.
Panel
Panel
LZC 1
Load circuit
wiring
LZC 12
12-circuit standard
panel with main
lugs shown
R