This series of industrial Ethernet switches is a single unit that can be
mounted directly into a 19-inch rack.Before installing, first confirm that there is
a suitable working environment, including power requirements, sufficient space,
whether it is close to other network devices and other devices to be connected.
Please confirm the following installation requirements:
Power requirements:AC220V standard product using a redundant
electrical power supply,the other power supply Please refer to product labels,
labels on the supply housing and associated instructions.
Environmental requirements: temperature-40°C~+85°C, relative
humidity5~95%(no condensation).
Grounding resistance requirements:<5;
According to the contract configuration requirements, check whether the
cable laying is in place and whether the fiber connector is suitable.
Avoid direct sunlight, away from sources of heat or areas with strong
electromagnetic interference.
Standard products are mounted in a 19-inch rack.Check for cables and
connectors required for installation.
Attention
Be sure to disconnect the power cord before installing or connecting an
Ethernet switch.Calculate the maximum possible current in each power line
and the common line, and observe all electrical information to know the
maximum current allowed by the lines of different widths.If the current
exceeds the maximum rated current, the wire will overheat and cause
serious damage to the equipment.
At the same time, you must also pay attention to the following:
Figure 2-6