Mechanical Installation; Siting Requirements; Monitor; Flowcell Assembly - ABB 7320 Series Instruction Manual

Dissolved organics monitor
Table of Contents

Advertisement

2 MECHANICAL INSTALLATION

Caution. Do not damage the equipment by
dropping, scraping or otherwise abusing it during the
installation process. Although the equipment is ruggedly
constructed, it contains precision optical components
which may be damaged if subjected to impacts or shock
loading.
2.1 Siting Requirements – Fig. 2.1

2.1.1 Monitor

Caution.
Mount in a location free from excessive vibration.
Mount away from harmful vapors and dripping fluids.
The monitor must be fixed to a wall or support in such a
position as to make reading the displays and operating the
keypad convenient. It is advisable to install a suitably switched
and fused isolating box to the right of the monitor, in a position
which allows the power to be switched on or off while standing
in front of the display.

2.1.2 Flowcell Assembly

The flowcell assembly is supplied on mounting brackets.
These must be fixed to a suitable vertical surface such that
convenient servicing and calibration is afforded. Allow suitable
space to the left and right of the unit for accessing the sensors.
Notes.
For ease of use it is recommended that the flowcell be
mounted at chest height.
The bracket fitted to the emitter module on a high
range flowcell is in two parts – see Fig. 2.5.
Maximum = 750 mm
Minimum = 200 mm
A – Distance between Instrument & Flowcell
0 °C minimum
B – Within Temperature Limits
IP65
C – Within Environmental Limits
Fig. 2.1 Siting Requirements
50 °C maximum