Commissioning, inspection, maintenance
Commissioning the heating system
Commissioning with the "commissioning assistant"
The commissioning assistant automatically guides you
through all the menus where settings have to be made.
For this, "Coding level 1" is automatically active.
Note
The following buttons may also be pressed during the
commissioning sequence:
ä To go back one step
å To display the commissioning menu structure
Note
If å is pressed during the commissioning
sequence, the current commissioning sequence
is terminated and will have to be restarted.
Turn on the ON/OFF switch and start the commissioning assistant
Turn on the ON/OFF switch on the control unit.
■
For initial start-up, the commissioning assistant
appears automatically.
Note
The commissioning assistant can also be started
manually:
–
Boiler not in operation
–
Control unit start-up
–
Press Ù and Ú simultaneously for approx.
5 seconds.
When the unit is first commissioned, the display is in
■
German.
Sprache
Deutsch
Bulgarski
Cesky
Dansk
Wählen mit
Fig. 35
■
Manually switching some appliance components dur-
ing commissioning enables the control unit to display
messages. These messages are not appliance
faults.
Commissioning sequence overview
Note
Other displays will be available depending on the set-
tings.
The following menu items may appear in sequence:
■
Select language
■
Enter ID number
■
Confirm boiler type
Load standard setting
■
48
!
Please note
An operating error at the "coding levels" may
result in damage to the boiler and the heating
system.
Follow the instructions in chapter "Codes".
DE
ê
ç
BG
ê
CZ
ê
DK
ê
(
■
Set date
Set time
■
Select cascade and boiler number
■
Select cascade charging
–
■
Configure supply system/charging scheme
For charging scheme with changeover unit:
–
Select changeover unit/number of wands
■
Select silo sensor fill level, fuel store
Set flue gas filter
■