CHAPTER 5 OPERATION TEST

Interoffice Transmission Line Test

INTEROFFICE TRANSMISSION LINE TEST
To confirm inter-office synchronization and speech quality using "In-Service" transmission lines,
do the following procedure:
STEP 1: Connect the transmission line to the MDF or CONN card.
STEP 2: Make busy the channels except the channel tested by CME5.
STEP 3: Confirm indication lamps on the DTI/PRT/BRT card, as per the following table.
• Alarm Indications on 24DTI
• Alarm Indications on 30DTI
• Alarm Indications on 24PRT
• Alarm Indications on BRT
STEP 4: Originate an outgoing call via trunk.
STEP 5: After an outgoing connection via trunks has been established, confirm inter-office
synchronization as follows:
• On the DTMF telephone set, keep pressing any dial button.
• Check to see if there are noise or abnormal tones.
• Do the above test again in the opposite direction.
STEP 6: Repeat the test for all channels. When completed, make idle all channels by CME5.
Page 190
(Table
5-1)
(Table
5-2)
(Table
5-3)
(Table
5-4)
2
NEAX2000 IVS
ISDN System Manual
ND-70919 (E), Issue 1.0

Advertisement

Table of Contents
loading

Table of Contents