PNA Series Microwave Network Analyzers
Tests and Adjustments
N5241A/42A
ANSI/NCSL Z540–1–1994 Verification
ANSI/NCSL Z540–1–1994 Verification
To meet the criteria for ANSI/NCSL Z540-1-1994, perform the preliminary checks and all
1
performance tests without stopping to repair or adjust
. Refer to
Figure 3-1
for test flow.
Print data at the completion of all the tests, even if you are aware that the analyzer did not
pass. If there is a failure, complete the verification before you troubleshoot, repair, and
adjust. After the failure has been corrected, repeat the entire set of performance tests and
generate a new set of data.
Figure 3-1
ANSI/NCSL Z540–1–1994 Test Path Verification Flowchart
1. Stop only in case of a catastrophic failure or cable connector damage
Service Guide N5242-90001
3-9