Specify a holiday that recurs once a year
•
Type 9999 in the YYYY field.
For example, type 9999 01 01 for New Years Day.
Specify a holiday that recurs once a month or once a day
•
Type 99 in the MM or DD field.
For example, type 9999 99 01 to specify that the first of every month is a holiday.
Type 9999 07 99 to specify that the plant is shut down every day in July for summer
vacation.
i
Note:
Make sure that your holidays do not overlap.
Change the duration of a holiday
By default the holiday has a Duration of 1 day. Change this to specify a longer holiday.
•
Type 9999-12-25 2 to specify a two day break beginning on December 25th.
Remove a holiday
•
Select the date in the Holidays defined list, and then click Delete Selected Holiday.
19.6
Network Node
Add a network node
1. Click Insert in the menu bar, then click Add Network Nodes.
The Add Network Node window appears.
Figure 108 Add Network Node
2. Type the number of nodes that you want to add in the Number to add field.
3. Type a description for the new node or nodes in the Tag field.
4. Click Add, and then click Close.
Using the Configurator