Operation
Precondition
Preparation
1
Open the circuit-breaker to decouple the
busbars.
The circuit-breaker is in the OPEN position.
The busbar is decoupled.
4
Insert the operating lever.
Turn it counterclockwise 180°.
The left-hand disconnector is in the OPEN
position.
7
Push the right-hand control gate to the left
and hold it.
The actuating opening of the right-hand
disconnector is open.
230/266
Decoupling the busbars
• Left-hand three-position disconnector in the CLOSED position.
• Right-hand three-position disconnector in the CLOSED position
• Circuit-breaker in the CLOSED position
• "Spring charged" indicator shows "spring charged"
• Check service readiness (see page 190, "Ready-for-service indicator")
2
Push the interrogation lever downwards and
hold it.
5
Remove the operating lever.
The interrogation lever and the control gate
move to their initial position.
8
Insert the operating lever.
Turn it counterclockwise 180°.
The right-hand disconnector is in the OPEN
position.
Revision 02 • INSTALLATION AND OPERATING INSTRUCTIONS • NXPLUS C • 806-9004.9
3
Push the left-hand control gate to the left
and hold it.
The actuating opening of the left-hand
disconnector is open.
5
Push the interrogation lever downwards
again and hold it.
9
Remove the operating lever.
The interrogation lever and the control gate
move to their initial position.