Removing from the
wooden pallets
806-9004.9 • INSTALLATION AND OPERATING INSTRUCTIONS • NXPLUS C • Revision 02
14.3

Unloading and transporting to the place of installation

Mortal danger due to transport units falling down!
During transport, the transport units can slip off the lifting gear and cause serious injury or
death.
➭ There must be no persons standing in the swinging area of lifted transport units.
➭ Please ensure that the lifting and transport gear used meets the requirements as regards
construction and load-bearing capacity.
➭ Observe the dimensions and weights of the transport unit (delivery note).
➭ Observe the center of gravity of the transport units.
➭ Do not step on the panels.
➭ The lifting gear must not exert any forces on the panel walls under load.
➭ Observe the instructions on the packing.
➭ Move the transport units in packed condition for as long as possible. Leave the transport
units packed after unloading for as long as possible.
➭ Do not damage the PE protective film.
➭ Hook the ropes into the hoisting tackle.
➭ Sling the ropes around the ends of the wooden pallets.
➭ Unload the transport units and set them down as close to the switchgear building as
possible in order to avoid unnecessarily long travel paths.
➭ Thoroughly clean the switchgear room, since extreme cleanliness is required for installation.
➭ Move the transport units on their wooden pallets as far as possible.
➭ Move the transport units to the switchgear room in the order of installation.
➭ Inside the building, move the transport units to the place of installation using a lifting truck,
fork-lift truck or on rollers.
➭ Set the transport units down in the correct sequence directly in front of the place of
installation (leave a clearance for installation).
➭ Remove the PE protective film.
➭ Remove the connection compartment cover (see page 185, "Removing and mounting the
connection compartment covers").
➭ Label the connection compartment cover with the panel number.
➭ Take out the transport bolts. Remove the metal plates placed underneath.
➭ In order to avoid damage to the panels, put the connection compartment cover back in
place.