7-Installation and Setup (continued)
7.19 Completion of Taping Heads
See Manual 2 for Complete Instructions:
Important – Do not cut against the apply roller -
roller damage could occur.

7.20 Outboard Tape Roll Holder

If you intend to use the outboard tape roll holder,
proceed as follows:
1 - Remove the lower taping head from the machine.
2 - Remove the tape drum bracket assembly, stud
spacer, and fasteners from the lower taping head.
3 - Install alternative wrap roller and bracket on the
head in place of tape bracket. Replace lower
head into machine.
4 - Install and secure tape drum bracket
assembly on the entry end of the lower frame
(as shown in Figure 7-22).

7.21 Preliminary Electric Inspection

Before connecting the machine to the mains please
carry out the following operations:
7.21.1 Make sure that the socket is provided with an
earth protection circuit and that both the mains
voltage and the frequency match the specifi -
cations on the name plate.
7.21.2 Check that the connection of the machine
to the mains meets the safety regulations in
your country.
7.21.3 The machine is fi tted with a main switch.
The user will be responsible for testing the
short-circuit current in its facility and should
check that the short-circuit amperage setting
of the machine is compatible with all the
components of the mains system.
700r3-NA
7.22 Machine Connection to the Mains
For technical specifi cations:
See Section 4 - Specifications
- Push the LATCHING EMERGENCY STOP
BUTTON.
- The main switch is normally turned OFF (O).
Connect the power cord supplied with the machine
to a wall socket using a plug which complies with
the safety regulations of your country.
7.23 Inspection of Phases
(For Three-Main Phases Only)
NA for this machine.