Commissioning
Recommended initialization procedure, via
parameter 14-22 Operation Mode
1.
Press [Main Menu] twice to access parameters.
2.
Scroll to parameter 14-22 Operation Mode and
press [OK].
3.
Scroll to [2] Initialisation and press [OK].
4.
Remove power to the unit and wait for the
display to turn off.
5.
Apply power to the unit.
5
5
Default parameter settings are restored during start-up.
The restore may take slightly longer than normal.
6.
Alarm 80, Drive initialised is shown.
7.
Press [Reset] to return to operating mode.
Manual initialization procedure
1.
Remove power to the unit and wait for the
display to turn off.
2.
Press and hold [Status], [Main Menu], and [OK] at
the same time while applying power to the unit
(approximately 5 s, or until a click is heard and
the fan starts).
Factory default parameter settings are restored during
start-up. The restore may take slightly longer than normal.
Manual initialization does not reset the following
frequency converter information:
Parameter 15-00 Operating hours
Parameter 15-03 Power Up's
Parameter 15-04 Over Temp's
Parameter 15-05 Over Volt's

5.4 Basic Programming

5.4.1 Commissioning with SmartStart

The SmartStart wizard enables fast configuration of basic
motor and application parameters.
SmartStart starts automatically at first power-up
or after initialization of the frequency converter.
Follow the on-screen instructions to complete the
commissioning of the frequency converter.
Always reactivate SmartStart by selecting Quick
Menu Q4 - SmartStart.
For commissioning without use of the SmartStart
wizard, refer to chapter 5.4.2 Commissioning via
[Main Menu] or the programming guide.
NOTICE
Motor data is required for the SmartStart set-up. The
required data is normally available on the motor
nameplate.
40
®
VLT
AQUA Drive FC 202

5.4.2 Commissioning via [Main Menu]

Recommended parameter settings are intended for start-
up and checkout purposes. Application settings may vary.
Enter data with power ON, but before operating the
frequency converter.
1.
2.
Illustration 5.2 Main Menu
3.
Illustration 5.3 Operation/Display
4.
Illustration 5.4 Basic Settings
5.
6.
Danfoss A/S © 11/2016 All rights reserved.
Press [Main Menu] on the LCP.
Press the navigation keys to scroll to parameter
group 0-** Operation/Display and press [OK].
1107 RPM
3.84 A
Main menu
0 - ** Operation/Display
1 - ** Load/Motor
2 - ** Brakes
3 - ** Reference / Ramps
Press the navigation keys to scroll to parameter
group 0-0* Basic Settings and press [OK].
0.0%
0.00A
Operation / Display
0-0
*
Basic Settings
0-1
*
Set-up Operations
0-2
LCP Display
*
0-3
*
LCP Custom Readout
Press the navigation keys to scroll to
parameter 0-03 Regional Settings and press [OK].
0.0%
0.00A
Basic Settings
0-03 Regional Settings
[0] International
Press the navigation keys to select [0] Interna-
tional or [1] North America as appropriate and
press [OK]. (This selection changes the default
settings for several basic parameters).
Press [Main Menu] on the LCP.
1 (1)
1(1)
0-
**
1(1)
0-0
*