AT510x DC Resistance Meter
14
3.3
Power Up
3.3.1
Line Power Connection
3.3.2
Power‐
up Sequence
3.3.3
Power‐up Defaults
3.3.4
Warm‐up Time
3.4
Measurement configuration
3.4.1
Connection Test side
Figure 3‐6
Connect to DUT
1.
RS232C interface.
2.
Handler interface.
3.
AC power cord receptacle and fuse holder
Power ON.
:
AT510x is power up, it performs self-tests on its Flash-Rom, RAM and momentarily
lights all segments and indicators. If a failure is detected, the instrument will not enter the
measurement state.
The power-on default will be the last configuration you saved.
AT510x is ready to be used as soon as the power-up sequence has completed. However, to
achieve the accuracy rating, warm up the instrument for 30 minutes.
Red logo testing BNC cables into the H in the first rotation;
black logo testing BNC cables into the L in the first rotation.
Red cable to test the high-pot
Black cable to test the low-pot
Power OFF.
Need help?
Do you have a question about the Anbai AT510PRO and is the answer not in the manual?