Inspur NF5280M5 Acceptance Manual page 7

Hide thumbs Also See for NF5280M5:
Table of Contents

Advertisement

Procedure
Expected result
Description
Table 1-4 PSU Hot Swap Function
Item
Objective
Prerequisites
Procedure
Copyright © Inspur Electronic Information Industry Co., Ltd.
1.
Install PSUs into the slots. You can install one to four
PSUs, and install filler modules in the vacant slots.
2.
Connect power cables to the PSUs, wait for 10 seconds,
and press the power button to power on the server.
1.
The PSUs and filler panel are installed smoothly and
properly.
2.
The PSUs fit the chassis properly.
3.
The PSUs are working properly and the indicators are
steady green when the server is being powered on.
4.
No abnormal noise is heard during the power-on
operation.
None
Content
To verify the PSU hot swap function.
The structure of the mainboard and hard disk backplane is
intact.
1.
Insert one PSU into the slot.
2.
Connect the power cables and wait 10 seconds till the
server is powered on.
3.
Insert second PSU into another slot. Connect power
cables to the PSU and check that the power status
indicator is steady green.
4.
Remove the first PSU from the slot.
5.
Insert the first PSU into the slot. Connect power cables to
the PSU and check that the power status indicator is
steady green.
6.
Remove the power cable from the second PSU
Inspur proprietary and confidential information
6

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents