Operation procedures

Operation procedures

Starting up

Before switching power on and starting up, a few things should be checked:
Make sure that the external exhaust system is switched on. If in doubt, please consult the inhouse
service technician.
Make sure that the compressed air supply system is switched on. If in doubt, please consult the
inhouse service technician.
Make sure that the chiller unit is switched ON.
Procedure
1.
Locate the main power switch in the front left
side panel, and switch power to ON.
The control panel will start up displaying ...
-
Machine illustration, ..
-
"2000TD loading", ..
-
"DuPont" flash screen.
2.
Then the display changes to show the home
view and the top line shows ..
"Ready to initialize"
.. continue with step 3. Do not press the
'Initialize' button yet.
NOTE: If by accident pressing the
'Initilize' button before turning the heat
on, the following message will be
displayed ...
January, 2020
Operation Manual|Cyrel FAST 2000TD
2-1

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the Cyrel FAST 2000TD and is the answer not in the manual?

Table of Contents