Short instructions
3.4
Fitting of the connection
housing
3.5

Test run

3.5.1

Bus connection (standard)

Figure B-3: AUMATIC bus
connection
Plug cover
Entries for bus
cables
.
After mains connection:
.
Insert the socket carrier (51.0) into the plug cover (50.0) and fasten it with
.
screws (51.01).
.
Clean sealing faces at the connection housing and the actuator housing.
.
Check whether O-ring is in good condition.
.
Apply a thin film of non-acidic grease (e.g. Vaseline) to the sealing faces.
Replace connection housing (50.0) and fasten bolts (50.01) evenly crosswise.
Fasten cable glands with the specified torque to ensure the required enclo-
sure protection.
Perform test run. Refer to the operation instructions for the actuator
(multi-turn actuator SA(R) ... / part-turn actuator SG ...).
Check limit and torque switching:
Check limit and torque switching, electronic position transmitter RWG or
potentiometer (option) and, where necessary, re-set.
The settings are described in the operation instructions to the actuator
(multi-turn actuator SA(R) ... part-turn actuator SG ... ).
For actuators with feedback signal (RWG, potentiometer), a reference oper-
ation has to be performed after the setting has been changed.
.
Perform reference operation:
Run actuator electrically (via the push-buttons OPEN and CLOSE) of the
.
local controls once to the end position OPEN and once to the end position
CLOSED.
If no reference operation is performed after changing the limit switching,
the feedback signal via the bus is not correct. The bus signals the missing
reference operation as warning.
For explosion-proof version (type designation: ACExC) see page 7.
For version with FO (fibre optics) refer to separate operation instructions
"AUMATIC AC 01.1 FO connection".
Disconnect power before removing the plug cover.
.
.
Loosen and remove plug cover (figure B-3). The connection board (figures
C-1, C-2 and C5) is located behind the plug cover.
Insert cable glands suitable for bus cables.
.
(The enclosure protection stated on the name plate is only ensured if suit-
.
able cable glands are used).
Seal cable entries which are not used with suitable plugs.
Connect bus cable. Refer to figures C-1 to C-6.
The termination resistors for channel 1 and channel 2 are switched in via
switches (S1) and (S2). Both switches are supplied in position 'OFF'. Only
connect the termination resistors (position 'ON') if the actuator is the final
station in the Profibus segment.
As soon as the termination resistors are switched on, the
connection to the next Profibus DP device is automatically
interrupted to avoid multiple terminations.
Table 2: Switch positions from S1 – S3
ON
Bus termination channel 1 ON
S1
OFF
Bus termination channel 1 OFF
ON
Bus termination channel 2 ON (option)
S2
OFF
Bus termination channel 2 OFF (option)
1SPC
one Profibus board
S3
2SPC
two Profibus boards (component redundancy, option)
Actuator controls AUMATIC AC 01.1 / ACExC 01.1
Profibus DP
5

Advertisement

Table of Contents
loading

This manual is also suitable for:

Aumatic acexc 01.1

Table of Contents