Sideshift Procedures

NOTES
• Operate (both front handles together or rear handles
together manually or via the remote (switch in F/B
position) to maintain level deck.
• Operate individual leg controls manually or via the
remote (switch in X1 position) to fine tune level deck.

Total Sideshifting to Streetside

NOTE
See Figure 3-6 for step drawings of what the trailer will
look like when shifting the entire trailer to the streetside.
1. Lower landing gear, uncouple truck from trailer, and
lift foot pads to clear ground.
NOTE
Suspension lower switch should be in "ON" position.
2. Fully extend front and rear streetside outriggers and
fully retract front and rear curbside outriggers.
3. Set all foot pads on ground and continue lifting trailer
until undercarriage tires clear the ground
(approximately 1").
4. The trailer can now be sideshifted to the streetside.
Insure that the trailer deck is level using bubble 
levels located on the front, rear, and both sides of 
trailer.
NOTE
The ladder must be in stowed position.
a. Slowly raise the two front outrigger control levers,
and the two rear outrigger control levers (See
Figure 3-3.) Feather the control levers to allow
the trailer to smoothly sideshift toward the
streetside.
b. For remote operation, push the side shift left
function on both the front section and rear
section of the remote control panel (See
Figure 3-5.) Feather the buttons to allow the
trailer to smoothly sideshift toward the streetside.
5. Before lowering trailer, release undercarriage brakes
(See Figure 3-3.) This allows the axles to roll back
under the trailer. Failure to release brakes will push
trailer forward when tires contact the ground.
6. After the trailer is on the ground, reset undercarriage
brakes (See Figure 3-3.)
For additional streetside sideshift movement, fully 
7.
retract front and rear streetside outriggers and fully 
extend front and rear curbside outriggers.  Repeat 
steps 3 through 6.
3-16

Total Sideshifting to Curbside

NOTE
See Figure 3-6 for step drawings of what the trailer will
look like when shifting the entire trailer to the streetside.
The outriggers will need to be shifted in the opposite
direction from the drawing to sideshift the entire trailer
toward the curbside.
1. Lower landing gear, uncouple truck from trailer, and
lift foot pads to clear ground.
NOTE
Suspension lower switch should be in "ON" position.
2. Fully retract front and rear streetside outriggers and
fully extend front and rear curbside outriggers.
3. Set all foot pads on ground and continue lifting trailer
until undercarriage tires clear the ground
(approximately 1").
4. The trailer can now be sideshifted to the curbside.
Insure that the trailer deck is level using bubble 
levels located on the front, rear, and both sides of 
trailer.
NOTE
The ladder must be in stowed position.
a. Slowly lower the two front outrigger control
levers, and the two rear outrigger control levers
(See Figure 3-3.) Feather the control levers to
allow the trailer to smoothly sideshift toward the
curbside.
b. For remote operation, push the side shift right
function on both the front section and rear
section of the remote control panel (See
Figure 3-5.) Feather the buttons to allow the
trailer to smoothly sideshift toward the curbside.
5. Before lowering trailer, release undercarriage brakes
(See Figure 3-3.) This allows the axles to roll back
under the trailer. Failure to release brakes will push
trailer forward when tires contact the ground.
6. After the trailer is on the ground, reset undercarriage
brakes (See Figure 3-3.)
For additional curbside sideshift movement, fully 
7.
extend front and rear streetside outriggers and fully 
retract front and rear curbside outriggers.  Repeat 
steps 3 through 6.