Checklist questions
Yes
No
Is there a sufficient number
of AC outlets for the
equipment?
Are the AC outlets on
different lines?
Does the input voltage
correspond to the PDU rack
specifications?
Are the input circuit
breakers adequate for
equipment loads?
Are uninterruptible power
supplies (UPS) in place?
Have all sources of
electrical interferences
been addressed?
Site access and security
Does the site enforce
access controls (for
example, will Hitachi
representatives need an
escort)?
Are all floors, stairs,
elevators, ramps, or
ladders adequate to
support the size and weight
of the storage system?
Will the equipment fit
through all doors and
corridors and in elevators?
If the site has a loading
dock, enter the maximum
access height: _____inches
or m.
Appendix A: Site preparation checklist
Site Preparation Guide for VSP G/F350, G/F370, G/F700, G/F900
52