Anchor Frame; Floor Mounted Frame; Figure 12 Frame Mount Footprint - GE Infinity M Series Installation Manual

High capacity with horizontal distribution, 13 u system with galaxy pulsar plus controller, 22u system with galaxy millennium ii controller, initial/supplemental frame, 22u system with supplemental frame and galaxy millennium ii controller
Table of Contents

Advertisement

NE-M Installation Guide

Anchor Frame

Ventilation space is required to the rear of the equipment: 4" to solid surface, 6" to heat producing surface.

Floor Mounted Frame

Using the 847135688 Floor Anchor Kit (recommended):
Anchor Type (Hilti)
(4) 12 mm Cap Bolts
Note: If using Equivalent Floor Anchors, make sure the floor anchors are rated for this application.
Note: An optional Supplemental Frame (without controller) may be located on either side of the Initial Frame (with
Millennium II controller).
Step
CAUTION: Health Hazard
Follow safe floor drilling procedures to prevent possible asbestos exposure.
1
Drill anchor holes.
2
Place frame and install floor anchors per manufacturer requirements.
3
Repeat for Supplemental Frame, if it is to be installed.
850050111
Issue 03 August 2017
Wrench
Torque
720 in-lb
19 mm
60 ft-lb
82 Nm
Action

Figure 12 Frame Mount Footprint

6 ft. and 7ft Frames
H5692448
17