Figure 3-17 Position for installing a battery grounding failure detector
----End

3.2.8 Routing Cables

3.2.8.1 Top Cable Routing

Context
Step 1 Open the front door, and remove the cover from the power distribution subrack, as shown in
Figure
Issue 06 (2020-01-10)
(1) Battery grounding failure detector
For details about how to install a battery grounding failure detector, see the UPS Battery Grounding
Failure Detector User Manual.
The basic rule is to route cables from inside out and from the bottom up.
After routing cables, use firestop putty to fill in the gap between the cables and the cabinet.
3-18.