3.
Note the updated Outlet Sequence heading at the top of the page that reflects your changes in the power-on
sequence.
In this example, Outlet 3 was selected and moved to the top of the sequence list to be powered on first.
In this example, the Outlet Sequence heading shows the (moved up) new sequence of outlets 3-2, 11-10,
and the original sequence of outlets 12-36.
4. Click in the Delay field for a specific outlet in the list and type a delay time (in seconds) before the outlet
powers on. The Delay default is 0.
5. Click Save.