Figure 4-8 Interconnecting cable terminals
Step 13 Check the end pressure gauge on the front of the cabinet. The pointer should be
in the green zone and the pressure reading should be greater than 1.6 MPa at
20°C. Record the reading of the pressure gauge. 8 hours later, observe the pressure
gauge again. The pressure reading should remain unchanged.
----End

4.3 Installing Cabinets

Securing Installation
Step 1 Determine the cabinet installation position. Draw mounting holes in the
installation position according to the drawing.