6.3.2 Installing Copper Bars and Cables Between Cabinets

Context
Procedure
Step 1 Remove the top cover (you do not need to reinstall it later).
Figure 6-8 Removing the cover
Step 2 Install transfer copper bars and battery cables by referring to the PowerPOD user
manual.
Step 3 Connect signal cables. Bind cables to the cabinet nearby.
● Do not bind signal cables and power cables together.
● RS485 cables and FE cables must be shielded cables.
● The figure uses the cable connection between the UPS and the SmartLi as an
Issue 01 (2022-05-12)
NO TE
The number and colors of cables in the figures are for reference only.
Connect the PoE port on the smart ETH gateway to the FE port on the
monitoring interface card.
If the UPS needs to connect to the SmartLi, connect the COM port on the
monitoring interface unit in the master SmartLi cabinet to the COM2 port on
the monitoring interface card.