Figure 6-11 Installing cables (8+8 scenario)
Figure 6-12 Installing cables (7+7 scenario)
Step 7 Reinstall the BCU.
Step 8 Press and hold the POWER ON/OFF button on the BCU for more than 2s. The
green indicator of the BCU blinks at 4 Hz.
Step 9 After the green indicator of the BCU blinks at 10 Hz, switch on the battery circuit
breaker on the SmartLi.
----End
6.8 Testing Batteries
6.8.1 Shallow Discharge Test