Figure 12
Task 7: Power the
components ON
Separate wires
around posts
Route cables from ports A4-FC02
and B4-FC02 to B side
Route cables from ports
A4-FC03 and B4-FC03 to A side
WAN cable routing on cable holders
1. Verify that all PDP switches and PDU circuit breakers (shown in
page
28) are in the OFF position. As the figure notes, the upper pair of PDUs are
installed upside-down from the lower pair, and the upper PDPs are not used.
2. Complete the EMC AC Power Configuration Worksheet and place it in a convenient
location, for use in verifying the data center power schemes.
3. Connect the main AC power cables from the lower PDPs into the site's power
sources. To ensure high availability, each cable must connect to a different power
source, as described in the EMC Best Practices Guide for AC Power Connections in
Two-PDP Bays.
Remove cap to route
cables, and then
replace cap
Detail
0
1
Installing the Hardware
2
3
zep-070a
Figure 13 on
Installing a cluster
27
Need help?
Do you have a question about the VPLEX with GeoSynchrony 4.2 and is the answer not in the manual?
Questions and answers