High Level Louvre Installation
To fit the louvre assembly in the high level position you place the EV795X392 glass under the louvre
frame. This should be held in place while the louvre frame is fixed in position, make sure the rebate
for the glass lines up with the front of the glazing bar before fixing. Drill pilot holes through the top
rail of the louvre frame and secure to the eaves
rail with 50mm CSK screws (Diagram 90).
Next, drill pilot holes through the glazing
bar (diagram 91), diagram 92 shows the
ideal angle of the 80mm CSK screw.
Make sure the rebate for the glass lines
up with the front of the glazing bar.
Diagram 89
Dia. 90
Dia. 91
11
Diagram 91
External
X-ray
38
Diagram 90
Diagram 92