Lantern Assembly
Now that the main frame has been assembled you can
begin to construct the lantern top which once assembled
will be lifted on whole.
Begin lantern assembly by constructing its gable ends. Drill
accurately placed pilot holes first (diagrams 50– 52), note
these screw heads will be visible externally. Use 50mm CSK
External
Diagram 51
screws to fix through the handed (EV1094 / EV1095)
lantern side corner mortices to pick up the cill section
(EV1089).
Again making sure that the pilot holts are accurately
positioned use 50mm CSK screws down through the
handed lantern top gable bars (EV1092 / EV1093) into the
side corners (diagram 51) .
Diagram 50
X 2
Dia. 51
Diagram 52
Dia. 52
9
External
23