Test Data Download; Download Over The Lcd - Huawei UPS5000-S Series User Manual

Ip42, 40 kva power modules
Hide thumbs Also See for UPS5000-S Series:
Table of Contents

Advertisement

UPS5000-S-(40 kVA-200 kVA)
User Manual (IP42, 40 kVA Power Modules)
Figure 5-17 Starting a capacity test
----End

5.6.4 Test Data Download

5.6.4.1 Download over the LCD

Procedure
Step 1 Insert a USB flash drive into the USB port on the MDU.
Step 2 On the main screen of the LCD, choose System Info. Tap
displayed.
Step 3 Choose USB Operations > Export Logs, and select a log download path.
Issue 03 (2020-01-10)
The capacity test automatically stops in any of the following cases:
The battery discharge voltage reaches the end of discharge (EOD) voltage plus 0.01 V.
The load fluctuation exceeds 10%.
An alarm is generated.
When the battery discharge voltage reaches the EOD voltage plus 0.01 V, the test is complete. The test
data is used as capacity test data. Save the capacity test data record with the largest discharge capacity in
a month as the capacity test data for the month. A maximum of recent 36 capacity test records can be
saved.
Copyright © Huawei Technologies Co., Ltd.
5 Operations
. The Maintenance screen is
161

Advertisement

Table of Contents
loading

Table of Contents