Landoll Brillion X108 Operator's Manual page 17

X-fold pulverizer, widths: 19’, 21’, 23’, 25’, and 27’
Table of Contents

Advertisement

Tighten all bo1ts to the torques specified in the chart above. It is important that bolts be kept tight at all times.
Loose bolts can cause breakage of parts. Check the tightness of bo1ts periodically and keep them tightened to
the torques specified above .
For wheel and pipe shaft assembly diagram see page 10.
1a. "XH" models with 20" notched wheels have rollers mounted on axle shafts from the factory . The
roller and green axle assembly must be assembled in the center section. Only the green axle pipe has
heavy wall high strength material.
lb. "X" models with 18" smooth wheels must have wheels assembled on axle shafts. Assemble the long
green axle first (27' models have three identical length axle shafts) with a A-86 end wheel on each
end with (25) A-46 wheels in between. Assemble the two wing axles the same with half the
remaining A-46 on each axle. Note the concave surface on the A-86 wheels must be to the outside of
each shaft assembly. Fasten wheels on axle with a clamp ring and U-bolt. The roller and green axle
assembly must be assembled in the center section. Only the green axle pipe has heavy wall high
strength material.
lc. "XC" models with 20" Crowfoot wheels must have wheels assembled on axle shaft. Assemble the
long green axle first (27' rnodels have three identical length axle shafts). Slide six 4-1/2" washers on
axle first. Slide a lD-939 wheel onto the shaft with the short hub adjacent to the welded ring. As
semble (16) lD-938 wheels onto shaft. Make sure that the direction of the wheel agrees with the
direction of arrows on the spokes. Finish the assembly with a 1D-940 wheel. Push wheels tight
against each other and fasten an end clamp and U-bolt next to the outer wheel to hold wheels on
shaft. The roller and green axle assenbly nust be assembled in the center section. Only the green
axle pipe has heavy wall high strength material.
Position the other two axles near the completed assembly as they would be in field use .The welded
rings on axles must be near the center assembly. Assemble a lD-939 wheel or lD-940 wheel first with
short hub adjacent to the welded ring. Assemble half the remaining lD-938 wheels on each axle.
Next, finish each axle as done on center axle. Make sure all arrows are the same direction.
683rev501