Kessel Aqualift F Installation Manual page 12

Pumping station for all wastewaters (with / without sewage) for underground / sub-surface installation
Table of Contents

Advertisement

After the upper section has been set to its final elevation and
slope, it is important to note the following:
In the case that the upper section and cover will be instal-
• Cobble stone / pavers installation
led in a stone / paver surface, it is important that the top of
the upper section is installed approx 2 cm higher than that
of the pavers. When the cobble stones are compacted the
upper section (with installed cover) should also be com-
pacted (be sure to tighten cover screws before compacting)
until it is level with the surrounding stones
In the case that the upper section and cover will be instal-
• Installation in traffic areas
led in a surface which is to handle Class D (40.0 metric ton
Possible installation depths
KESSEL – Pumpstation Aqualift F in System 1000 Inspection Chamber
Installation depths from 1.63 to 5.13 meters
KESSEL – Pumpstation Aqualift F in System 800 Inspection Chamber
Installation depths from 1.46 to 1.96 meters
4. Installation and Assembly
load classes), a 18cm thick, 2m x 2m B25 concrete load dis-
tributiont plate must be poured around the upper section.
The concrete support plate should be steel re-enforced
and comply with any local regulations. A drawing of this load
support plate is available from KESSEL upon request.
• In some instances it may be required that the lower sec-
tion of the upper section be sawed off in order to obtain the
correct installation depth. This cut should be made as
evenly as possible and any remaining loose edges should
be filed away. The included manhole cover removal key as
well as the User´s Manual for the pumping system should
be stored in a protected dry area in the vacinity of the con-
trol unit.