Table 8. Appliance installation checklist (continued)
Task
Description
U
Section 9: Completing the installation
The trained ProtecTIER specialist or LBS
9–1
h
representative releases the fully operational
system over to the customer and refers the
customer to the IBM System Storage
ProtecTIER User's Guide for Enterprise Edition
and Appliance Edition, IBM form number
GA32-0922 for further information.

Installing the frame

This topic contains the procedure to install the appliance frame.
About this task
This task lists the steps to physically install the AP1 frame at the customer site.
Note: Do not remove the server retention screws. The screws must be removed
only to perform service on the server.
Procedure
Perform the following steps to install the AP1 frame.
1. Maneuver the TS7650 AP1 frame into the designated location.
2. Use the 43-mm wrench (P/N 31L8313) supplied with the TS7650 to make the
3. If the frame is in its final location (that is, if the customer does not anticipate
24
IBM System Storage TS7650 ProtecTIER Deduplication Appliance: Installation Roadmap Guide
See the precautions in "Frame safety" on page xv before you begin the
installation process.
Note: If the frame is installed on a raised floor, ensure that the hole cutout in
the floor is located under the rear of the frame.
following adjustments to the frame leveling pads:
a. Loosen the locknuts on the leveling pads.
b. Adjust the height of the leveling pads until the frame is approximately level
and parallel to the floor, and the casters are off the floor.
This adjustment can be accomplished with one full turn of the leveling pad
after it is in contact with floor.
c. Tighten the locknuts on the leveling pads by moving the locknuts up to
bottom of the frame.
needing to move it again), remove the shipping components securing the server
or servers to the frame by performing the following steps:
CAUTION:
Failure to remove the hardware discussed in steps 3a through 3d on page 25
can result in damage to the server sliding mechanisms when attempting to
move the server to the service position.
a. Remove the four retention screws securing Server A to the shipping
brackets mounted to the frame as shown in Figure 11 on page 25.
Where to find information
This document: Chapter 9, "What to do next,"
on page 137

Advertisement

Table of Contents
loading

This manual is also suitable for:

Ts7600Ts7650gTs7610

Table of Contents