Glazing (part 2)
Before you start glazing you should place the bar capping around
the building again so you have it to hand when needed. If you
have the aluminium capping remember to insert the glazing
rubber and trim it to length (diagram 91).
Slide the first piece of roof glass into place, be careful to support
this and try to slide it up one roof bar until it reaches the other.
When lowered into the glass stops the glass should fit either side
of the rebate in the roof bar (diagram 92).
Diagram 90
Section
EV0982
Glazing
Rubber
EV0992M
Section
Diagram 91
EV824X1106X30
Diagram 92
External
EV824X1106X30
14
External
Diagram 93