High Level Louvre Installation
To fit the louvre assembly in the high level position you place the EV795X392 glass under the louvre
frame. This should be held in place while the louvre frame is fixed in position. Drill a pilot hole
through the top rail of the louvre frame and secure to the eaves rail with a 50mm screw (Diagram 60).
Diagram 61
External
X-ray
Next, drill a pilot hole through the glazing bar
(diagram 61), diagram 62 shows the ideal angle
Diagram 60
of the screw. Make sure the rebate for the glass
lines up with the front of the glazing bar.
Diagram 62