Installing the UC Open

Installing the UC Open
1
Mount the controller. (page 4)
2
Wire the controller for power. (page 5)
3
Set the controller's address. (page 5)
4
Wire the controller to the BACnet MS/TP or BACnet ARC156 network (page 6).
5
Wire inputs and outputs (page 7).
6
Wire devices to the controller's Rnet port. (page 11)

Mounting the UC Open

WARNING
When you handle the UC Open:
• Do not contaminate the printed circuit board with fingerprints, moisture, or any foreign material.
• Do not touch components or leads.
• Handle the board by its edges.
• Isolate from high voltage or electrostatic discharge.
• Ensure that you are properly grounded.
Screw the UC Open into an enclosed panel using the mounting slots on the coverplate. Leave about 2 in. (5 cm)
on each side of the controller for wiring. Mounting hole dimensions 5 1/4" (13.3 cm) between mounting slot
center lines.
UC Open
Installation and Start-up Guide
4
CARRIER CORPORATION ©2019
All rights reserved