9.1
Before Turning ON the Power
After wiring, be sure to check the items below before turning ON the power supply to
the programmable controller.
Item
Unit mounting status
Power supply
Check input/output
terminals
Setting of control unit
Matsushita Automation Controls
Description
S Does the unit type match the device list during the design
stage?
S Are all of the units firmly fixed?
S Is operating voltage supplied correctly ?
S Is the power supply cable properly connected?
S Does the wiring of connector and terminal match ?
S Is the operating voltage of I/O correct ?
S Are the connector of I/O properly connected ?
S Is the wire size correct ?
S Is the mode switch set to the PROG. mode ?