Step 4 – Alignment of
components in preparation for
drilling and pinning
· Thread the Top Clamp into the
threaded hole so that it extends the top
latch to the proper position for pinning.
The Top Bolt Clamp will assure that
the top latch is in the correct position
for final installation.
· Prepare the lifting platform installation
jig by removing the two wing fasteners
and their washers
· Introduce the lifting platform jig up
through the under side of the shutter as
shown
· Using the two wing fasteners and their
washers, secure the lifting platform jig
to the shutter.
The lifting platform jig will now be in position
to allow sliding the lifting platform (shown in
step 2) so that it rests against the shelf of the
jig.
Continued on next page.............