Power On / Off Process

NOTE:
After turning off a system, wait at least ten seconds before turning it on again. The system may not be
able to boot if power is recycled too quickly.
3-4-4-1

Scanner Power On

1.) Connect the Power Cable to the back of the system.
2.) Connect the Main Power Cable to a hospital grade power receptacle with the proper rated voltage.
Never use an adapter that would defeat the safety ground.
3.) Switch ON the Circuit Breaker at the rear of the system.
Figure 3-8 Circuit Breaker and Power Cable on Back of Scanner
A- Circuit Breaker
B- Power cable
When power is applied to the scanner and the rear Circuit Breaker is turned ON, power is distributed to
the Transformer Assembly
3-14
Approv e d Docu m ent - 5213326-100TPH_r3.pdf Page 71 of 252
3
EVISION
Section 3-4 - Completing the Installation
LOGIQ™ A3 S
M
ERVICE
ANUAL
A
B

Advertisement

Table of Contents
loading

Table of Contents