Installing A Fan Unit - Huawei UPS5000-S-1200 kVA User Manual

Hide thumbs Also See for UPS5000-S-1200 kVA:
Table of Contents

Advertisement

UPS5000-S-1200 kVA
User Manual
Figure 3-45 Installing mounting plates
Step 8 Connect signal cables to the maintenance bypass unit.
Figure 3-46 Connecting signal cables
Step 9 Install anchor baffle plates for the maintenance bypass unit.
Step 10 Reinstall the front and rear covers, and install the side panel removed from the input and
output unit on the maintenance bypass unit.
----End

3.2.5.3 Installing a Fan Unit

Configure the fan unit if you install the cabinet against the wall.
Issue 04 (2019-06-25)