Procedure
Step 1 Use a pallet truck to transport the UPS to the installation position.
Step 2 Remove the UPS outer packing.
Step 3 Remove the bolts that secure the UPS to the pallet and remove the UPS from the pallet.
Figure 3-5 Removing the pallet from the UPS
----End
3.1.5 (Optional) Splitting the Bypass Unit and Input and Output
Unit
Context
If the door of the power distribution equipment room is not wide enough to move the UPS,
you can split the bypass unit and input and output unit before the movement.
Issue 04 (2019-06-25)
Only trained personnel are allowed to move the UPS. Use a pallet truck to transport the
UPS box secured to a wooden support to the installation position.
To prevent the UPS from falling over, secure it to an electric pallet truck using ropes
before moving it.
To prevent shocks or falls, move the UPS gently. After placing the UPS in the installation
position, unpack it with care to prevent scratches. Keep the UPS steady during unpacking.
If the UPS installation environment is in poor condition and the UPS will be stored for a
long time after it is unpacked, wrap the UPS with the original plastic coat to prevent dust.
Copyright © Huawei Technologies Co., Ltd.