7. For Stud Partition Walls
a. For stud partition wall installations make sure that a wooden noggin is in place
directly behind the final valve position. The supplied First Fix Pipe Guide MUST
be used to mark the pipework centres, check that the pipe guide is level and
mark the pipework centres. DO NOT drill through the pipe guide.
SIDE VIEW
b. Make sure the holes drilled through the noggin are square and level to the
mounting surface.
Pipe Clip
c. Plumb supplies using 15 mm copper pipework, make sure a minimum 150
mm of pipe extends from the front surface of the noggin. We recommend the
use of a pipe clip to secure the pipework within the wall, this MUST be placed
a minimum of 150 mm from the elbow joint.
1285246-W2-D
First Fix
Pipe Guide
Min: 19 mm Dia.
Max: 25 mm Dia.
150 mm
Mark these two Holes
150 mm
12
TOP VIEW

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Agile s eco b97cAgile store ev+ b97dAgile ev+ b97cAgile erd+ b97dAgile sense erd+ b97d

Table of Contents