9.2 Installation, electrical

Fig. 5: Undertake the electrical installation for (A) the transfer pump and (B) metering pump
4.
Install the flushing adapter.
Mount the flushing adapter to the wall.
n
Connect the flushing adapter to the diluting water stopcock.
n
A
B
4
3
P_HYD_0026_SW
Make the electrical cabling connections - see Fig. 5.
1. - Insert the plug of the suction lance level switch (chemical feed
container) in the "Level switch connector" at the metering
pump.
2. - Plug the signal cable from a control into the "External oper‐
ating modes connection" at the metering pump.
3. - Insert the plug of the decanting vessel level switch in the
"Level switch connector" at the decanting pump.
4. - Only for collecting pan with leakage probe: Undertake the
electrical installation for the leakage probe so that an alarm is
triggered in the event of a leak.
5. - Install an emergency cut-off switch for both pumps.
6. - Connect both mains cables to the mains outlets.
4 1 2