Installation; 9.1 Installation, Hydraulic - ProMinent DULCODOS Hydrazin Operating Instructions Manual

Hydrazine metering systems
Table of Contents

Advertisement

9

Installation

9.1 Installation, hydraulic

A
Fig. 3: A. Screw parts together, B. make the internal piping connections
B
1.
Assemble the supplied parts of the hydrazine dosing system and
screw together with the connectors of the chemical feed container to
form a tight fit - see Fig. 3 A.
1. - Decanting pump
2. - Metering pump.
3. - Diluting water feed
4. - Activate carbon filter. Also secure using the metal angle!
5. - Hand crank
2.
Make the internal piping connections - see Fig. 3 B.
1. - Decanting pump suction line for the storage tank. Use hose
clips as necessary!
2. - Vapour recovery line from the dosing tank for the storage tank.
Use hose clips as necessary!
3. - Decanting line from the decanting pump to the metering con‐
tainer
4. - Suction line of the metering pump
Installation
P_HYD_0021_SW
15