Chapter 2
Installing the System
Preparing for System Installation
This section provides information about preparing for system installation, and it includes the following
topics:
Installation Guidelines
To prevent the system from overheating, do not operate it in an area that exceeds the maximum
Warning
recommended ambient temperature of: 35° C (95° F).
Statement 1047
The plug-socket combination must be accessible at all times, because it serves as the main
Warning
disconnecting device.
Statement 1019
This product relies on the building's installation for short-circuit (overcurrent) protection.
Warning
Ensure that the protective device is rated not greater than: 250 V, 15 A.
Statement 1005
Warning
Installation of the equipment must comply with local and national electrical codes.
Statement 1074
When you are installing a system, use the following guidelines:
Installation Guidelines, page 2-3
Rack Requirements, page 2-4
Equipment Requirements, page 2-4
Slide Rail Adjustment Range, page 2-4
Plan your site configuration and prepare the site before installing the system. See the
Preparation Guide
for the recommended site planning tasks.
Ensure that there is adequate space around the system to allow for servicing the system and for
adequate airflow. The airflow in this system is from front to back.
Ensure that the air-conditioning meets the thermal requirements listed in the
page
A-1.
Ensure that the cabinet or rack meets the requirements listed in the
Ensure that the site power meets the power requirements listed in the
page
A-1. You can use an uninterruptible power supply (UPS), if available, to protect against power
failures.
Cisco UCS S3260 Storage Server Chassis Installation and Service Guide
Preparing for System Installation